Kameno 12 MW – Bulgaria

Project Info

  • Construction Date

    October 2011 - March 2012

  • Category

    Civil Engineering, Solar EPC

Works done:

  • Project management
  • Site management
  • Security on-site 24 h
  • Temporary storage area
  • Reception and Unloading of all the materials

Civil works:
– Execution of buildings foundation
– Execution of Customer Switching room, control and CCTV Building, and meteorological station foundations
– Trenches and conduits (supply and installation)
– Fencing (supply and installation)
– Demolitions

Mechanical works:
– Topographical works
– Ramming of the piles
– Structure Mounting System
– Mounting of the PV panels

Electrical works:
– Installation of AC cabling between inverters and transformers.
– Installation of DC cabling between inverters and string combiner boxes.
– Installation of DC cabling between string combiner boxes and panels.
– Plugging of all panels together.
– Installation of auxiliary supply between the distribution board and inverter.
– Fitting of fuses (left forward) in each string combiner box.
– Installation of data cabling between the Aurora logger, inverters, and string combiner boxes.
– Installation of 1 off-earth rod and earth lead to each string combiner box.
– Connection of each substation earth mat linking the inverters and transformers together.
– Carry out final landing/termination of all installed cabling.
– Testing and commissioning
– As-built documents