ENOC Futurisic Retail Fuel Station
The Futuristic Retail Fuel Station was an ingenious structure built within the expo master site, in Dubai, to be a flagship of Emirates National Oil Company. The structure was intended to achieve LEEDs Gold certification at the minimum.
Representatives from Viking were involved in the design, installation, and commissioning of this futuristic structure. The project was of bespoke nature and customized modules that suit the architectural intent of the structure were designed, procured, and installed.
Technical Data:
Total installed capacity: 137.54 KWp
Specific yield: 1471 KWh/KWp/year
Performance ratio: 72.59 %
Total Grid feed-in for the first year: 203.09 MWh/year
Scope:
- Preparation of Detailed Solar & Structural Design for the System.
- Coordinate closely with concerned authorities to get project approvals
- Equipment supply and installation
- Comply with all the applicable HSE requirements
- AC and DC work
- Testing and commissioning of the system
- Provide the As-built drawings.
- Project Management for the entire PV system.
- Project handover
The Futuristic Retail Fuel Station was an ingenious structure built within the expo master site, in Dubai, to be a flagship of Emirates National Oil Company. The structure was intended to achieve LEEDs Gold certification at the minimum.
Representatives from Viking were involved in the design, installation, and commissioning of this futuristic structure. The project was of bespoke nature and customized modules that suit the architectural intent of the structure were designed, procured, and installed.
Technical Data:
Total installed capacity: 137.54 KWp
Specific yield: 1471 KWh/KWp/year
Performance ratio: 72.59 %
Total Grid feed-in for the first year: 203.09 MWh/year
Scope:
- Preparation of Detailed Solar & Structural Design for the System.
- Coordinate closely with concerned authorities to get project approvals
- Equipment supply and installation
- Comply with all the applicable HSE requirements
- AC and DC work
- Testing and commissioning of the system
- Provide the As-built drawings.
- Project Management for the entire PV system.
- Project handover